When: 2024

Location: Kingdom of Saudi Arabia (KSA)

Industry: Petrochemical

Client Overview

A major petrochemical operator in KSA required a high-capacity, reliable temporary power solution to support critical production operations. The client needed prime power availability with strict safety and performance standards to ensure uninterrupted plant operations during the project period.

case-study

Challenges

The petrochemical facility required continuous, stable medium-voltage power capable of supporting critical production processes without interruption. The solution had to be deployed as a turnkey system, safely integrated with existing infrastructure, and operated under stringent industrial safety requirements.

Solution

Byrne delivered a turnkey 10.4 MW temporary power plant, including:

  • 10.4 MW medium-voltage power solution designed for prime power operation

  • Full engineering design, installation, and commissioning

  • Integrated medium-voltage distribution and protection systems

  • Continuous operation and monitoring by Byrne’s technical team

Result

The temporary power plant provided a reliable and efficient energy supply, enabling uninterrupted petrochemical production. Byrne’s turnkey delivery ensured safe operation, operational continuity, and high client confidence throughout the project duration.