Solution Provided
Byrne delivered a mast climber solution engineered to match the façade installation requirements.
Double-decker configurations were used to support simultaneous work across multiple levels, aligned with the façade panel height and installation sequence.
Extended platform configurations allowed concurrent teams to operate efficiently on each unit, reducing repositioning and improving workflow continuity.
Byrne managed engineering design, mobilisation, and installation, with all units deployed within 27 days to meet project milestones.
This Solution Offered
- Parallel work across multiple teams, accelerating installation cycles
- Reduced reliance on scaffolding, lowering setup time and site congestion
- Improved material handling and workflow efficiency at height
- Stable and safe working platforms aligned with façade requirements
Operational Support
Byrne provided continuous on-site support throughout the project:
- Daily technical support for 31 mast climbers
- Operator training delivered to 18 site personnel
- Ongoing inspection, maintenance, and troubleshooting
- Average response time of 2.5 hours
- Equipment uptime maintained at approximately 97%